Case Study · SB 721 · CSLB #1060736
SB 721 Balcony Ledger & Framing Rebuild — 72-Unit Apartment Community, Gilroy
24 stacked balconies reframed where they attach to the building and where they rest on their posts — the two connections that looked sound from above and had decayed underneath.
Balcony RepairProject facts
- Location
- Gilroy, CA
- Service
- Balcony Repair & Restoration
- Property
- Three-story garden apartment community, post-supported stacked balconies
- Units
- 72
- Client
- Property management company
- Scope
- 24 balconies reframed · new ledgers and joist hangers · new posts and corner beams · existing railings reinstalled
- Timeline
- 8 weeks · residents in place
- Completed
- Q3 2026
- Budget range
- $210k–$270k
01 The situation
The challenge
From the balconies themselves, nothing looked urgent: the surfaces were usable and the metal railings were solid. The SB 721 inspection found the problems underneath, at two connections. At the wall, water running down the stucco had soaked the ledger boards that hold the balconies to the building — the wood had gone dark along its length, the joist hangers had rusted, and the ledger had decayed at its ends. At the outer corners, the tops of the posts had split and gone soft directly under the beams, where water collected on the end grain, and the bolted plates holding post to beam were corroding.
The layout made the repair harder. The balconies are stacked on the same lines of posts, so the third-floor balcony depends on the framing of the second-floor balcony below it. Opening one level without support would have left the level above without its load path, and all three floors — including the ground-floor patios under the balconies — stayed occupied for the whole job.
02 Execution
What we did
We worked one stack at a time, from the ground up:
Shored each stack from the ground before cutting anything, so the balcony above stayed supported while the one below was opened
Removed the decayed ledgers, bolted new pressure-treated ledgers through to the building framing with flashing lapped above them, and hung new joists in new galvanized hangers
Replaced the decayed posts and corner beams with new pressure-treated members set on concrete piers, joined with new galvanized plates and through-bolts
Reinstalled the existing metal railings on the new framing and removed the shoring only after each level was complete and checked
03 Outcome
The result
Every reframed balcony now carries its load through a new ledger, new hangers and new posts, and the connection at the wall is flashed so water running down the stucco no longer reaches the wood. The SB 721 findings were closed inside the 120-day repair window, and reusing the existing railings kept the work focused on the framing the inspector had flagged.
Results at a glance
- 24 balconies reframed at the ledger, joists and posts
- New ledgers bolted to the building, with flashing above
- Corroded hangers and post plates replaced with new galvanized hardware
- Repairs finished inside the 120-day SB 721 window
What the client received
- SB 721 repair documentation for the property file
- Photo record of every ledger and post connection, before and after
- Shoring and repair plan for the stacked balconies
- Workmanship warranty on all reframed balconies
Transformation
Before & After
Post and corner beam


Ledger at the wall


“From the balconies everything looked fine. The rot was at the wall and at the top of the posts, where you only see it from underneath.”
Keep exploring
More Balcony Repair Projects
Balcony RepairWood-to-Composite Balcony Decking Replacement for an HOA Community — Morgan Hill32 balconies moved from painted wood to capped composite decking after SB 326 findings — with the framing…View case study
Balcony RepairBalcony Replacement with Trex Composite Decking — 18 Balconies, AntelopeThe rot had already reached the beams and posts. We rebuilt the framing under every balcony and re-decked…View case study
Balcony RepairBalcony & Elevated Walkway Replacement — 24 Balconies, LodiEvery balcony and second-floor walkway rebuilt from the framing up — new waterproof deck system, new code-height guardrails,…View case study