Case Study · Replacement permits · CSLB #1060736
Patio Deck Rebuild on Existing Concrete Piers — 30-Unit Townhome Community, Stockton
30 ground-floor patio decks rebuilt from the post bases up — the concrete piers and galvanized post bases were checked and stayed, and the decayed framing and decking above them were replaced.
Deck RepairProject facts
- Location
- Stockton, CA
- Service
- Deck & Balcony Replacement
- Property
- Two-story townhome community, a ground-floor patio deck behind each unit
- Units
- 30
- Client
- Property management company
- Scope
- 30 patio decks rebuilt on existing concrete piers · new joists, rim boards and wood decking · piers and post bases checked and reused · privacy walls kept in place
- Timeline
- 7 weeks · residents in place
- Completed
- Q3 2026
- Budget range
- $210k–$260k
01 The situation
The challenge
The patio decks behind the townhomes had weathered gray, the boards had cupped, and the rim boards had split at the corners where they joined. Lifting boards showed why: the joists and rim boards were water-damaged at their ends, so new decking alone would have gone onto framing that was already failing.
The other quote the owner had in hand was a full replacement from new footings: dig out every concrete pier among the planting and the privacy walls, pour new ones, then build. That would have meant more cost, more disruption on each patio and longer time without a deck, for piers nobody had actually checked. The owner wanted to know first what was sound and what was not.
02 Execution
What we did
We checked the piers and post bases before deciding what to rebuild:
Lifted boards and probed the joists, rims and posts on every deck, and checked each concrete pier and post base for movement, level and corrosion
Removed the decking, joists and rim boards down to the post bases, keeping the concrete piers, the galvanized post bases and the privacy walls between units
Framed new joists and new rim boards on the existing supports, with the rim boards bolted together at the corners
Laid new wood decking on every deck and closed the permit with a final inspection on each building
03 Outcome
The result
Every patio deck now has new framing and new decking, set on piers that were checked rather than assumed. Keeping the piers and post bases removed the excavation and concrete work from the scope, and leaving the privacy walls standing meant each patio stayed private while its deck was rebuilt. The work closed with a permit and final inspection on file.
Results at a glance
- 30 patio decks rebuilt on the existing concrete piers
- Concrete piers and galvanized post bases checked and reused
- New joists, rim boards and wood decking on every deck
- Privacy walls between units left in place
What the client received
- Permit and final inspection sign-off
- Probe results for every deck, with the pier and post base check recorded
- Workmanship warranty on all rebuilt decks
- One decking specification for future replacements
Transformation
Before & After
Patio deck


Rim board on concrete piers


“The concrete piers were fine; the wood on top of them wasn't. They rebuilt the decks on what was already there, and our residents kept their privacy walls the whole time.”
Keep exploring
More Deck Repair Projects
Deck RepairPodium Terrace Paver Replacement & Drainage Correction — 120-Unit Apartment Community, Concord6,500 square feet of pavers lifted, the membrane underneath tested, pedestals reset and drains cleared — so rain…View case study
Deck RepairMulti-Level Ocean-View Deck & Stair Replacement — San MateoStepped decks cascading down a bluff, replaced surface and stairs first — because on a multi-level deck the…View case study
Deck RepairEntry Porch Deck Replacement Across a Townhome Row — PleasantonTwenty-four front-door decks rebuilt with air beneath them and planting pulled back from the edge — because these…View case study